Specify the site’s required voltage, frequency in hertz, phase arrangement, phase rotation, neutral arrangement and connected-load characteristics. Confirm each item against the latest site distribution drawings and the selected generator’s current specification sheet before ordering. Do not infer the configuration from the country, region or a preferred generator model alone.
A procurement record, not a wiring diagram. Confirm these fields against site drawings and the manufacturer's current documents with the responsible electrical professional.
1. Start with the site electrical basis
Build the specification from the existing or planned electrical system. Collect these documents before requesting a firm quotation:
- The latest single-line diagram
- Utility or facility electrical data
- Equipment nameplates and load schedules
- Transfer-switch information
- Generator connection and terminal diagrams
- Confirmation from the responsible electrical engineer
Also record the intended operating mode, such as standby, prime or parallel operation, and ask the responsible electrical professional whether that choice creates project-specific control, protection or approval requirements. This guide helps you prepare the procurement record; it does not replace project-specific electrical design or approval.
2. Define voltage precisely
Record the voltage fields used by the site documentation:
- Line-to-line voltage
- Line-to-neutral voltage, where applicable
State where the recorded voltage applies and identify whether the site includes single-phase loads, three-phase loads, or both. Confirm the required neutral arrangement with the responsible electrical professional and the generator manufacturer.
A Cummins specification excerpt presents available-voltage examples as line-to-neutral/line-to-line pairs, including 120/208, 127/220, 220/380 and 277/480 V for a stated 60 Hz product scope. These are examples from that published specification, not universal availability or a recommendation for your site. The selected manufacturer must confirm the available winding connection, terminal arrangement and any permitted voltage changes in the current datasheet and connection diagram. Cummins product specifications
3. Confirm frequency and phase
Put the frequency and phase in separate, explicit fields. Treat the following as example inputs to verify, not as exhaustive options:
- Frequency: for example, 50 Hz or 60 Hz
- Phase: record the site requirement and confirm the offered arrangement
- Phase rotation: record the sequence required by the site documentation
The Cummins product listing shows separate 50 Hz and 60 Hz entries and identifies the displayed examples as single-phase products. It does not establish what your facility requires or the full range of available configurations. Cummins generator listing
Verify the required frequency and phase from the site documentation and connected-equipment information. Ask the manufacturer to state the offered phase arrangement and phase rotation on the quotation and final documentation rather than relying on a model name or a general catalogue description.
4. Record neutral and transfer interfaces
Record the neutral arrangement required by the site documentation and transfer equipment. Ask the responsible electrical professional and the manufacturer to confirm any required neutral switching arrangement, terminal details and related project interfaces. Include the generator terminal diagram, transfer-equipment information and approved single-line diagram in the technical review.
This guide does not determine grounding, isolation or protection requirements and does not provide connection or repair procedures. Keep those decisions with the responsible electrical professional and the project’s qualified parties.
5. Match the configuration to actual loads
A load review should capture the characteristics that the supplied sizing guidance identifies as relevant:
| Load information | Procurement question |
|---|---|
| Motor starting | Which motors must start, and what starting information is available? |
| Voltage dip and frequency dip | What performance information does the supplier provide for the relevant load application? |
| Harmonic distortion | Are nonlinear loads present, and what information is required for them? |
| Motors, VFDs, UPS systems and battery chargers | Which of these load types are connected or planned? |
| Load application and recovery | What voltage and frequency recovery information should be stated in the quotation? |
Kohler’s sizing material discusses motor starting, voltage dip, frequency dip, harmonic distortion and load types including motors, VFDs, UPS systems and battery chargers. Use those subjects when preparing the load schedule, without assigning a performance class or acceptance limit unless the project specification requires it. Kohler motor-starting guidance
Load application affects generator voltage and frequency. A technical Kohler paper explains that transient criteria include voltage and frequency limits and recovery times; agree the applicable criteria with the project team rather than assuming them from nominal ratings. Kohler transient-performance paper
6. Buyer checklist before issuing the order
Ask the responsible engineer or facility owner to confirm every item below:
- Voltage, line-to-line, as required by the site documentation
- Voltage, line-to-neutral, if applicable
- Frequency required by the site system; confirm the manufacturer’s offering
- Phase arrangement required by the site system; confirm the manufacturer’s offering
- Required phase rotation
- Neutral arrangement and any transfer-equipment requirements
- Operating mode: standby, prime or parallel, with project-specific implications confirmed
- Motor-starting requirements
- Presence of motors, VFDs, UPS systems or battery chargers
- Required voltage and frequency recovery information
- Current manufacturer datasheet and voltage-connection diagram
- Approved single-line diagram and transfer-equipment information
No project-specific electrical values were supplied for this guide, so none should be filled in as assumed examples. Treat unresolved fields as open questions before procurement. The final quotation should repeat the agreed voltage, frequency, phase, neutral arrangement and rotation, while the final engineering review confirms that the complete system matches the site.
Sources & scope
- Generators | Cummins Quiet Diesel Generators | Cummins Inc. The supplied excerpt lists separate 50 Hz and 60 Hz entries and displayed single-phase generator examples; it does not establish the requirements of a particular site.
- C1000D6ED C900D6E C800D6E C750D6E C600D6E The supplied excerpt gives a 60 Hz product scope and lists example available voltages in line-to-neutral/line-to-line form, including 120/208, 127/220, 220/380 and 277/480 V.
- Sizing Generators for Motor Starting: APractical Guideto ... The supplied excerpt supports reviewing motor starting, voltage dip, frequency dip, harmonic distortion and load types such as motors, VFDs, UPS systems and battery chargers.
- ISO%208528-5%20and%20Generator%20Transient%20Performance_WP.pdf The supplied excerpt discusses transient voltage and frequency limits, recovery times and the effect of applying or removing load; it does not set a requirement for this project.
General procurement guidance. Worked examples are illustrative; final selection requires the selected manufacturer's documentation and a project-specific engineering review.